Discussion about this post

User's avatar
Winston G Adams's avatar

A search show island peak demand of in 2023 at 1730 MW during a polar vortex event.

For 2024 it was 1691 MW

For 2025 it was 1384 MW

For 2026 early Jan it was 1229- 1446 MW

Isn't the peak well below the forecast one by the Muskrat Falls promoters? Does that forecasting engineer still have his job?

Generally there seems to be no growth in peak demand, and that without a robust efficiency program,(worst in Canada), which could reduce peak demand further.

Winston G Adams's avatar

A max of 780 MW was brought over the LIL, which is about 95 % of MW generation capacity, more than I expected they could do at present. This suggests a transmission loss of about 5 %, but TL may be higher if some other Labrador Power was on that line, which is rated at 900 MW. If TL was about 10% then another 42 MW over and above MFs capacity would have been transmitted to get 780 MW received here at Soldier's Pond.

What is the present reliability factor for the LIL? How many hours per year downtime from unexpected events resulting in no power or reduced power, if one or two of the DC conductors are malfunctioning?

Basically the LIL is not very reliable, and they must have been "shit baked" that it might fail.

That would have been a Dark Nfld event if more than a few hour duration, with the 600 MW of island hydro off for a few days. That was a rare event, frazzle ice on the intakes, but a possible event to be anticipated, and more so with climate change, as we can expect shitty weather more often.

Yes we will always need thermal for backup on the Avalon, due to the exposure of the lines coming unto the Avalon, as to severe icing, that can take down the strongest of lines.

In the 1970s, when I worked there, I looked at photos of lines taken down by icing with 6 inches of ice build up. The steel towers buckled and went down and the steel sold as scrap. They learned the most vulnerable sections and rebuilt stronger. But the LIL is generally not build to those standards, and so at high risk. Then Holy rood thermal was relatively new, now largely obsolete.

I wonder how much power was imported on the Maritime Link, as there is no obligation that they supply power.

I feel that Liberty Consultants pulled out of NL, as adviser to the PUB, due to Nlfd Hydro not doing the right steps to make our system better.

major rethink is needed for island power that is reliable, and thermal as backup.

Island Demand was about 1450 MW, about 20 % lower than 1800 MW that can be expected at times.

How many of the those in the MF fiasco are still involved in Nfld Hydro operations, in any department?

Will there be a big shake up by the new government?

6 more comments...

No posts

Ready for more?